Dhola-Sadiya bridge on Brahmaputra

  • Total Project Cost(TPC) : Rs. 938 crore
  • Appointed date:17.06.2011
  • Status of completion: Completed 
  • Length of approach road :19.38 km
  • Length of main bridge and viaduct:9.13 km
  • Bridge to provide direct inter- state connectivity between eastern parts of Assam (Dhola on NH-37) and Arunachal Pradesh (Roing on NH-52 ), cater for strategic requirement, will reduce the travel time from Dhola to Roing via Tezpur from 14 Hours to 30 minutes
  • Dedicated to the Nation by Hon’ble PM on 26.05.2017

Dhola Sadiya 1